Job cost, WIP, and margin at completion
Job cost and WIP with projected margin at completion against the bid, change orders by age, and labor productivity, by job, division, and project manager.
The challenge
Job cost lives in accounting and progress in the field, so the question that matters, will this job finish at the margin it was bid, is answered only at closeout.
What we build
The build models cost to date, budget, earned value, and change orders into a governed model, defines percent complete and projected margin at completion once, and flags jobs fading from their bid.
In the build
- A governed model over job cost, budget, and change orders.
- Projected margin at completion against the bid, by job.
- WIP, percent complete, and change-order aging in one view.
Outcomes
- Margin erosion caught mid-job, not at closeout.
- Change orders tracked against the cost they cover.
- WIP and margin read together across every active job.
Data sources
Microsoft stack
The dashboards
The report we build, re-skinned here in the browser. Switch pages with the tabs and hover the charts. Representative, not a specific client.
WIP & Margin Fade
— October 31, 2026- Marcus Ellery-$4.7M
- Laura Fenn-$1.4M
- Grace Holm-$406K
- Kevin Oduya-$353K
- Sam Delacroix-$215K
- Priya Natarajan-$209K
- Dana Whitfield-$119K
- Tom Brandt+$4K
| Job | Division | PM | Contract | % compl. | Bid | Proj. | Δ pts | Over/(under) |
|---|---|---|---|---|---|---|---|---|
| J25044 Fairmont Apts | Plumbing | M. Ellery | $5.6M | 79% | 16.4% | 2.6% | -13.8 | +$1.1M |
| J24872 Summit Park Hosp | Plumbing | M. Ellery | $6.7M | 70% | 14.9% | 2.4% | -12.6 | +$839K |
| J25074 Stonebridge Med | Plumbing | M. Ellery | $21.5M | 74% | 17.8% | 6.3% | -11.5 | +$3.4M |
| J24734 Pinecrest Apts | Plumbing | M. Ellery | $4.1M | 72% | 17.5% | 6.2% | -11.4 | +$520K |
| J24579 Westfield Mixed-Use | Plumbing | L. Fenn | $23.0M | 20% | 15.0% | 9.5% | -5.5 | +$236K |
| J23688 Stonebridge Med | Plumbing | L. Fenn | $3.9M | 54% | 14.7% | 10.2% | -4.5 | +$328K |
| J24146 Riverside Hotel | Plumbing | S. Delacroix | $3.6M | 53% | 15.5% | 12.1% | -3.4 | +$258K |
| J23469 Lakeview Brewery | Process Piping | P. Natarajan | $5.5M | 62% | 21.7% | 18.6% | -3.1 | +$381K |
The contractor sees each job's projected margin against its bid while there is still time to act, with the change orders and labor hours behind the fade.
A representative build that shows what we deliver, not based on a specific client. Named-client work is shared only with written permission.